In August 2007, a draft urban planning agreement was presented as part of the negotiations between Pratdip Town Council and the Planas del Rey Urbanisation Maintenance Entity (EUCC).

This seven-page document contains a proposed resolution for the Pratdip Town Council, followed by the draft agreement itself. Its purpose is to define the responsibilities of the Council and the EUCC for organising, financing and overseeing the works needed to complete the urbanisation.

Main provisions of the draft agreement

The document includes the following provisions:

  • a change from the compensation system to the cooperation system, under which the Town Council would take responsibility for the administrative procedures and organisation of the works;
  • full financing of the works and associated technical costs by Planas del Rey property owners;
  • continued maintenance responsibilities for the EUCC, with owners remaining liable for their usual contributions throughout the works;
  • the award of the works contract through a public tendering procedure and the establishment of a committee made up of representatives of the Town Council and the EUCC to oversee the project;
  • payment in instalments, beginning with 35% when the contract is awarded, followed by two payments of 15%, with the balance payable upon final acceptance of the works;
  • the transfer of the infrastructure and shared services to the Town Council once the works have been completed, followed by the procedure to dissolve the EUCC.

An agreement still awaiting approval

The draft includes certain safeguards concerning oversight of the works, completion deadlines and the maintenance of agreed unit prices. However, it does not set an overall ceiling on the final cost of the project, particularly if changes or additional works become necessary.

The document reproduced here is a draft agreement. It does not establish that the agreement was formally approved or signed.

At the general meeting held on 12 August 2007, property owners rejected the agreement, mainly because of concerns that the final cost of the works could exceed the original budget.

For further background on the negotiations and the reasons for the rejection, see our historical article: 2007 – A new agreement rejected despite a project estimated at around €7 million.


Original document – August 2007

August 2007 – Proposed council resolution and draft urban planning agreement (in Spanish)

Open the PDF file in a new tab